October 14th – Our loan closed (recorded) today.
October 15th - I was at the county today to file for our building permit!
October 22nd - Our excavator, Warren Ewing, moved on site to begin the excavation. He started with the utilities, digging the ditch for the electric.
October 23rd - The trench was completed, conduit placed, and PGE inspected. The pad for our electrical vault was delivered and placed. We ordered our PGE service.
October 26th – Warren dug the ditch for the water line and started the foundation dig out. It was raining like crazy. I would like to say Warren is a dedicated professional. He did a first class job for us, and his perseverance is Herculean. He got the job done in spite of some of the worst weather I could imagine. He brought industrial lighting with him, so he could work until way after dark. We are so fortunate to have him on our team.
October 28th - Our building permit is ready to be picked up!
October 29th – PGE installed our electrical service. I picked up the building permit and the septic permit at Clackamas County. I turned in our Lot Ready form to Adair Homes. We are ready to roll!!!
November 3 -4th - The septic tank was installed.
November 10th - The concrete crew started the forms for the foundation.
Yes, that really is a little guy on the crew. Paul, the concrete installer, works with his family. Those kids work as hard as any full grown man. We were skeptical, but soon were impressed.
November 13th - The foundation was poured today.
November 20th - The framers laid the floor of the house. This is what it looks like with the floor joist placed. We went up in one of our boomlifts to get this picture.
November 23rd - 24th -The plumber did the rough plumbing.
November 25th - Sub-floor installed and walls are starting to go up!

November 26th - THANKSGIVING!
December 1st - The walls are finished and the interior walls are framed. I can see where all of the rooms are now.
December 2nd - Trusses are going up!
It is such a beautiful day out, and the house is really looking like a house!
December 9th - 11th - The roof was installed, as were the gutters, windows installed, bathtub and shower fixtures placed, furnace and duct work installed and the exterior of the house was wrapped in Tyvek. WOW!